Artroom Expansion 7

Major Sheathing Operations are Complete!
The roofing is done thanks to the lads from Collum Roofing. In addition to roofing the expansion, we had them tear off and re-roof the original building. Despite the fact that shingles have spiked in price,(lots of oil goes into roofing shingles) They tore it off, carted it off, laid new 30# paper, new drip edge, and roofed it in 2 1/2 days. An outstanding job.

Meanwhile, I finished the sheathing, the cutouts for the exterior outlets and lights, roof vents, and the exhaust fan for removing the excess heat buildup from running the kilns. The caulking is almost complete. This room will be airtight.
Artroom28

The electrician finished his rough in, so we have 2 50 amp circuits for the kilns, GFCI's for the exterior outlets and separate circuits for lighting and outlets.
Artroom30 Next up is the pumbing rough in for the cleaning sink, insulation and drywall.

The interior party wall is almost taped off.
Artroom29
Hopefully I can get this hung by this weekend.