Lightyear Sunken Bath Episode 14 Done

The LSB is in the history books. Here is a recap.

Before
Here is the view from the doorway into the bath from the master bedroom. Note on the left is the hinged door. In the case where someone might be using the toilet and someone else rushed in, it would give kneecapping a new meaning.6a00d8345237e469e201157245f42f970b-800wi

The tile is tired and the ‘tub’ is a sunken nightmare. Notice the window (single pane double thick tempered) in the back wall that looks out into the storage area that the client had enclosed sometime ago. That outside door faces east and the long wall faces south. It made this room hotter than hell most of the year and cold the rest.

After

Here is the view from the same spot.
We removed the tile, filled in the sunken tub area, installed a new glass block window, insulated, skim coated, installed a jacuzzi tub, surrounded it with solid surface, installed a Jeeves Heated Towel Bar,(which was the only item not obtained locally in either the Orange or Blue stores) installed grab bars in the shower/tub area, and with the extra space on the front side of the tub created built in shelving and a magazine rack for parking pleasure. Also with the installation of a pocket door, ‘kneecapping’ is a thing of the past. We also installed a tall mirror for last minute inspections. Just to the left of the tall mirror are two switches. These are to shut off the power to the jacuzzi when not in use. The controls are way too  convenient to small children.

Jacuzzi, Solid Surface and New Glass Block.

Jacuzzi, Solid Surface and New Glass Block.


Back wall and storage area

Before

We also had the door to the sort of storage/dog area to address. Since the bathroom had so little storage and we knew early on that we would be installing a water heater for this room and the bath on this end of the house, we decided to parcel this space, insulate, drywall and tile it.
6a00d8345237e469e201157151bc7c970c-800wi

After

We installed a bi-fold door that closely matched the existing doors in the rest of the house.

6a00d8345237e469e201157246193c970b-800wi

Vanity Area Before

The only change to the vanity area was the replacement of the light fixtures, installing new faucets to match the brushed nickle finish of the new shower toys, and replacement of the cabinet pulls.

6a00d8345237e469e2011572461d72970b-800wi

After

6a00d8345237e469e2011572461e10970b-800wi

There it is.

Lightyear Sunken Bath Episode 13 Details

The LSB is down to the bits. Major work is complete.  We are down to the details.
Toilet
The glass block although only a 6×6” unit adds enough light so you can find it without needing a flashlight.

New Throne with Light and reading rack

New Throne with Light and reading rack

The toilet is an American Standard Cadet model. It is a low flush, comfort height, extended bowl with one of the fastest flushes I have seen.

Pocket Door. Adds much usable space to the room.

Pocket Doors add space

Shower Front
Here we opted for a shower massage shower over the simple head provided by the manufacturer.

Shower head with natural lighting

Also we installed a curved shower curtain rod.
Shower Back
On the left or long wall is a 24” grab bar. On the right side of the window is a 12” grab bar. On the right is a 54” high Jeeves Heated Towel Bar.

Tub and floor details

Early Morning
Since the long wall faces east and gets the morning sun, here is a sample of the glass block display.

Morning Light through Glass Blocks

Morning Light through Glass Blocks


Before and After 09 – One Project Closer DIY Contest!!

Before_and_after_blue The gang at One Project Closer are having their Second Annual Before and After Contest. Prizes and a Donations for Habitat for Humanity hang in the balance! Get off your ass and submit your DIY Project NOW!

Lightyear Sunken Bath Episode 12 Solid Surface Installation

Before and After
Here is where we started and here is where we are finishing.

Before and After

Before and After


In our last episode I was working on the access panel for the jacuzzi. Having sorted that out, I spent time finishing up the skim coating and priming and painting in anticipation of the solid surface.
Tuesday Morning.

Morning Light

Morning Light

Painting is done on the soffit ceilings and the walls up to a few inches behind where the solid surface will go.
Here are a couple of the lads from Pro Tops Inc. setup and cutting the large side panel.

ProTops lads assembling walls

ProTops lads assembling walls

On the left is a portable swamp cooler as the temperature was over 100. With the canopy it is a pleasant place to work if you have to work outdoors in Arizona in the summer.

The big panel has been installed and they are building the template for the back panel. They built the sides of the three glass block openings and attached them to the panel before installing it. Slid Right In.

Long Wall installed. The lads are building the template for the back wall.

Long Wall installed. The lads are building the template for the back wall.

The templating system that they use consists of 1/8” luan ply and hot melt glue to measure for the panels. Works slick. When you are working on material that has no room for error, it is important to get it right.

Here is the finished product.

Finished and done

Finished and done


Here is the access panel for whoever may have to work on this in the future.

Finish Access Panel

Finish Access Panel

It is mechanical and all mechanical things break down eventually. The guy who will have to fix this years down the road will thank me. So will the client not having to tear up the bathroom to fix a pump or leak.